Sewerage Construction Schedule Phase 2, Both Contracts, Week of August 3rd

sewer

    TOWN OF HARWICH, MASSACHUSETTS

SEWERAGE WORKS IMPROVEMENTS PHASE 2 – CONTRACT #1

ROBERT B. OUR COMPANY

SEWER PROJECT

 

CONSTRUCTION SCHEDULE – WEEKLY UPDATE

Date Submitted:  August 3, 2020

One Week Look Ahead (08/03-08/07)

  • Mainline Sewer Crew # 1
    • Continue Installation of the Gravity Mainline on Spruce Grove
  • Mainline Sewer Crew # 2
    • Continue Installation of the Gravity Service on Sherwood
    • Commence Installation of the Gravity Mainline on Landron

 

Two Week Look Ahead (08/10-08/14)

  • Mainline Sewer Crew # 1
    • Continue Installation of the Gravity Mainline on Spruce Grove
  • Mainline Sewer Crew # 2
    • Continue Installation of the Gravity Mainline on Landron

 

Three Week Look Ahead (08/03-08/07)

  • Mainline Sewer Crew # 1
    • Commence Installation of the Gravity Mainline on Round Cove Road
  • Mainline Sewer Crew # 2
    • Continue Installation of the Gravity Services on Landron

 

 

Please note that this is a projected schedule and will be adjusted accordingly based on the Contractor’s actual progress and the weather. On an as needed basis auxiliary crews will be performing testing, installing inverts, raising castings, paving , and performing general cleanup at various locations throughout the project area.

TOWN OF HARWICH, MASSACHUSETTS
SEWERAGE WORKS IMPROVEMENTS PHASE 2 – CONTRACT #2
CONSTRUCTION SCHEDULE – WEEKLY UPDATE
One Week Look Ahead (08/03-08/07)
 Mainline Sewer Crew #1
o Start Nor’east Drive at Church (C-7)
 Scheduled WM shut down on Monday
 Road Closed between Church Street and Rt 39


Two Week Look Ahead (08/10-08/14)
 Mainline Sewer Crew #1
o Continue Nor’east Drive from Church (C-7)
 Road Closed between Church Street and Rt 39


Three Week Look Ahead (08/17-08/21)
 Mainline Sewer Crew #1
o Continue Nor’east Drive from Church (C-7)
 Road Closed between Church Street and Rt 39


Please note that this is a projected schedule and will be adjusted accordingly based on the Contractor’s
actual progress and the weather. On an as needed basis auxiliary crews will be performing testing,
installing inverts, raising castings, paving , and performing general cleanup at various locations throughout
the project area.