Sewerage Construction Schedule Phase 2, Both Contracts, Week of July 6th

sewer

    TOWN OF HARWICH, MASSACHUSETTS

SEWERAGE WORKS IMPROVEMENTS PHASE 2 – CONTRACT #1

ROBERT B. OUR COMPANY

SEWER PROJECT

 

CONSTRUCTION SCHEDULE – WEEKLY UPDATE

Date Submitted:  July 6, 2020

 

One Week Look Ahead (07/06-7/10)

  • Mainline Sewer Crew # 1
    • Continue Installation of the Gravity Main on Somerset Road

 

Two Week Look Ahead (07/13-7/17)

  • Mainline Sewer Crew # 1
    • Continue Installation of the Gravity Main and Services on Somerset Road

 

Three Week Look Ahead (07/20-7/24)

  • Mainline Sewer Crew # 1
    • Continue Installation of the Gravity Main and Services on Somerset Road
    • Commence Installation of the Gravity Mainline on Sherwood Road (S8-1-S17-4)

 

Please note that this is a projected schedule and will be adjusted accordingly based on the Contractor’s actual progress and the weather. On an as needed basis auxiliary crews will be performing testing, installing inverts, raising castings, paving , and performing general cleanup at various locations throughout the project area.

TOWN OF HARWICH, MASSACHUSETTS
SEWERAGE WORKS IMPROVEMENTS PHASE 2 – CONTRACT #2
CONSTRUCTION SCHEDULE – WEEKLY UPDATE

One Week Look Ahead (07/06-07/10)
• Mainline Sewer Crew #1
o Continue Williamsburg Ave from S25-2 (C-27)
 Road closed between Bay Road and Rt 39

Two Week Look Ahead (07/13-07/17)
• Mainline Sewer Crew #1
o Continue / finish on Williamsburg Ave from S25-2 (C-27)
• Road Closed between Bay Road and Rt 39

Three Week Look Ahead (07/20-07/24)
• Mainline Sewer Crew #1
o Start Fredericksburg Ave from S25-1 (C-26)
 Road Closed between Bay Road and Rt 39

Please note that this is a projected schedule and will be adjusted accordingly based on the Contractor’s actual progress and the weather. On an as needed basis auxiliary crews will be performing testing, installing inverts, raising castings, paving , and performing general cleanup at various locations throughout the project area.