Sewerage Construction Schedule Phase 2, Both Contracts, Week of May 26th

sewer

    TOWN OF HARWICH, MASSACHUSETTS

SEWERAGE WORKS IMPROVEMENTS PHASE 2 – CONTRACT #1

ROBERT B. OUR COMPANY

SEWER PROJECT

 

CONSTRUCTION SCHEDULE – WEEKLY UPDATE

Date Submitted:  May 26, 2020

 

One Week Look Ahead (05/26—05/29) No Work 05/25

  • Mainline Sewer Crew # 1
    • Continue Installation on RT 137 –Sherwood to Halls Path

Installation of Force Main and Side Road “Stub Offs”

  • Subcontractors performing various tasks at various locations

Testing, Inverts, Casting Adjustments, Mandrel (RT 137 & RT 39)

  • Mainline Sewer Crew # 2
    • Perform Restoration at various locations for a partial week.

TwoWeek Look Ahead (06/01—06/05)

  • Mainline Sewer Crew # 1
    • Continue Installation on RT 137 –Sherwood to Halls Path

Installation of Force Main

  • Subcontractors performing various tasks at various locations

Testing, Inverts, Casting Adjustments, Mandrel (RT 137 & RT 39)

  • Mainline Sewer Crew # 2
    • Commence Installation of the Gravity Main on RT 137 by Queen Anne Road. For the Installation of the Parshall Flume.

  ** Detour for Flume Work  **

Three Week Look Ahead (06/08-06/12)

  • Mainline Sewer Crew # 1
    • Continue Installation on RT 137 –Sherwood to Halls Path

Installation of Forcemain

  • Subcontractors performing various tasks at various locations

Testing, Inverts, Casting Adjustments, Mandrel (RT 137 & RT 39)

  • Mainline Sewer Crew # 2
    • Commence Installation of the Gravity Main on RT 137 by Queen Anne Road. For the Installation of the Parshall Flume and sewer services in that area.
    • Continue Restoration of RT 137 Corridor.

Please note that this is a projected schedule and will be adjusted accordingly based on the Contractor’s actual progress and the weather. On an as needed basis auxiliary crews will be performing testing, installing inverts, raising castings, paving , and performing general cleanup at various locations throughout the project area.

TOWN OF HARWICH, MASSACHUSETTS
SEWERAGE WORKS IMPROVEMENTS PHASE 2 – CONTRACT #2
CONSTRUCTION SCHEDULE – WEEKLY UPDATE

One Week Look Ahead (05/26-05/29)
• Mainline Sewer Crew #1
o Complete Church Street FM & laterals and clean-up (C-1, C-36)
o Mill Church Street
 Road Closed between Bay Road and Queen Anne

Two Week Look Ahead (06/01-06/05)
• Mainline Sewer Crew #1
o Start Bay Road from S4-1 (C-23)
o Pave Church Street
 Road Closed between Rt 39 and Church Street

Three Week Look Ahead (06/08-06/12)
• Mainline Sewer Crew #1
o Continue on Bay Road from S4-1 (C-23)
 Road Closed between Rt 39 and Church Street

Please note that this is a projected schedule and will be adjusted accordingly based on the Contractor’s actual progress and the weather. On an as needed basis auxiliary crews will be performing testing, installing inverts, raising castings, paving , and performing general cleanup at various locations throughout the project area.