Sewerage Construction Schedule Phase 2, Both Contracts, Week of June 1st

sewer

TOWN OF HARWICH, MASSACHUSETTS SEWERAGE WORKS IMPROVEMENTS PHASE 2
– CONTRACT #1 ROBERT B. OUR COMPANY SEWER PROJECT CONSTRUCTION SCHEDULE –
WEEKLY UPDATE
Date Submitted: June 1, 2021

One Week Look Ahead (06/01/21- 06/04/21) • Pump Station Crew # 1 o Continue Working on Spence’s Trace & RT 137 Pump Station Site’s & Flume ▪ Station Startups and programing

Two Week Look Ahead (06/07/21- 06/11/21) • Pump Station Crew # 1 o Continue Working on Spence’s Trace & RT 137 Pump Station Site’s & Flume ▪ Station Startups and programing

Three Week Look Ahead (06/14/21- 06/18/21) • Pump Station Crew # 1 o Continue Working on Spence’s Trace & RT 137 Pump Station Site’s & Flume ▪ Station Startups and programing

Please note that this is a projected schedule and will be adjusted accordingly based on the Contractor’s actual progress and the weather. On an as needed basis auxiliary crews will be performing testing, installing inverts, raising castings, paving , and performing general cleanup at various locations throughout the project area.

TOWN OF HARWICH, MASSACHUSETTS SEWERAGE WORKS IMPROVEMENTS PHASE 2
– CONTRACT #2 CONSTRUCTION SCHEDULE –
WEEKLY UPDATE

One Week Look Ahead (06/01-06/04) • Pump Station Crew #1 o Continue work at Church Street south pumping station o Continue work at Church Street north pumping station o Continue Harden Lane grinder pump station

Two Week Look Ahead (06/07-06/11) • Pump Station Crew #1 o Continue work at Church Street south pumping station o Continue work at Church Street north pumping station o Continue Harden Lane grinder pump station

Three Week Look Ahead (06/14-06/18) • Pump Station Crew #1 o Continue work at Church Street south pumping station o Continue work at Church Street north pumping station o Continue Harden Lane grinder pump station

Please note that this is a projected schedule and will be adjusted accordingly based on the Contractor’s actual progress and the weather. On an as needed basis auxiliary crews will be performing testing, installing inverts, raising castings, paving , and performing general cleanup at various locations throughout the project area.