Sewerage Construction Schedule Phase 2 Week of Dec.6

sewer

  TOWN OF HARWICH, MASSACHUSETTS

SEWERAGE WORKS IMPROVEMENTS PHASE 2 – CONTRACT #1

SEWER PROJECT

 

CONSTRUCTION SCHEDULE – WEEKLY UPDATE

Date Submitted:  December 6, 2019

 

One Week Look Ahead (12/9-12/13)

  • Mainline Sewer Crew # 1
    • Continue Installation on Route 39

**Detour for part of the week **

  • Mainline Sewer Crew # 2
    • Continue Installation of Sou West Drive
    • Continue Installation on RT137

** Detour **

Two Week Look Ahead (12/16-12/20)

  • Mainline Sewer Crew # 1
    • Subcontractors performing various tasks at various locations
  • Mainline Sewer Crew # 2
    • Continue Installation on RT137

** Detour **

 

Three Week Look Ahead (12/23-12/27) ** No Work on 12/25 **

  • Mainline Sewer Crew # 1
    • Subcontractors performing various tasks at various locations
  • Mainline Sewer Crew # 2
    • Continue Installation on RT137

** Detour **

 

 

Please note that this is a projected schedule and will be adjusted accordingly based on the Contractor’s actual progress and the weather. On an as needed basis auxiliary crews will be performing testing, installing inverts, raising castings, paving , and performing general cleanup at various locations throughout the project area.

 

 