Sewerage Construction Schedule Phase 2 Week of March 24th

sewer

  TOWN OF HARWICH, MASSACHUSETTS

SEWERAGE WORKS IMPROVEMENTS PHASE 2 – CONTRACT #1

SEWER PROJECT

 

CONSTRUCTION SCHEDULE – WEEKLY UPDATE

Date Submitted:  March 23, 2020

One Week Look Ahead (03/23-3/27) 

Mainline Sewer Crew # 1 

Continue Gravity Sewer Installation on Chris Jo Beth 

Subcontractors performing various tasks at various locations 

Testing, Inverts, Casting Adjustments, Mandrel (RT 137 & RT 39)

Mainline Sewer Crew # 2 Continue Installation on RT137  

Complete Installation on RT 137 Lights to Austin Road 

Commence Installation on RT 39 from Lights to Austin Road

Services at Various Locations

Commence Installation RT 137  Austin Road and Lighthouse Charter School 

** Detour **

Two Week Look Ahead (03/30--4/3) 

Mainline Sewer Crew # 1 

Continue Gravity Sewer Installation on Chris Jo Beth 

Subcontractors performing various tasks at various locations 

Testing, Inverts, Casting Adjustments, Mandrel (RT 137 & RT 39)

Mainline Sewer Crew # 2 Continue Installation on RT137  

Between Austin Road and Lighthouse Charter School 

** Detour  / Night Work ?**

Three Week Look Ahead (04/06--4/10) 

Mainline Sewer Crew # 1 

Continue Gravity Sewer Installation on Chris Jo Beth 

Subcontractors performing various tasks at various locations 

Testing, Inverts, Casting Adjustments, Mandrel (RT 137 & RT 39)

Mainline Sewer Crew # 2 Continue Installation on RT137  

Between Austin Road and Lighthouse Charter School 

** Detour  / Night Work ? ** 

 

 

Please note that this is a projected schedule and will be adjusted accordingly based on the Contractor’s actual progress and the weather. On an as needed basis auxiliary crews will be performing testing, installing inverts, raising castings, paving , and performing general cleanup at various locations throughout the project area. 