Sewerage Construction Schedule Phase 2 Week of October 9
Posted on: October 2, 2019 - 11:15am
TOWN OF HARWICH, MASSACHUSETTS
SEWERAGE WORKS IMPROVEMENTS PHASE 2 – CONTRACT #1
SEWER PROJECT
CONSTRUCTION SCHEDULE – WEEKLY UPDATE
Date Submitted: October 9, 2019
One Week Look Ahead (10/15-10/18) ** No Work 10/14**
- Mainline Sewer Crew # 1
- Continue Installation on RT 39
** Detour **
- Mainline Sewer Crew # 2
- Continue Installation on RT137
** Detour **
Two Week Look Ahead (10/21-10/25)
- Mainline Sewer Crew # 1
- Continue Installation on RT 39
** Detour **
- Mainline Sewer Crew # 2
- Continue Installation on RT137
** Detour **
Three Week Look Ahead (10/28-11/1)
- Mainline Sewer Crew # 1
- Continue Installation on RT 39
** Detour **
- Mainline Sewer Crew # 2
- Continue Installation on RT137
** Detour **
Please note that this is a projected schedule and will be adjusted accordingly based on the Contractor’s actual progress and the weather. On an as needed basis auxiliary crews will be performing testing, installing inverts, raising castings, paving , and performing general cleanup at various locations throughout the project area.
Attachment | Size |
---|---|
hsi_10.9.2019_-_update.pdf | 521.07 KB |