Sewerage Construction Schedule Phase 2, Both Contracts, Week of April 5th

sewer

TOWN OF HARWICH, MASSACHUSETTS SEWERAGE WORKS IMPROVEMENTS PHASE 2
– CONTRACT #1 ROBERT B. OUR COMPANY SEWER PROJECT CONSTRUCTION SCHEDULE –
WEEKLY UPDATE
Date Submitted: April 5, 2021

One Week Look Ahead (04/05/21-04/09/21) • Pump Station Crew # 1 o Continue Working on Spence’s Trace & RT 137 Pump Station Site’s o Cleanup at Various Locations of Road Shoulders o Continue Working on the Parshall Flume

Two Week Look Ahead (04/12/21-04/16/21) • Pump Station Crew # 1 o Continue Working on Spence’s Trace & RT 137 Pump Station Site’s o Cleanup at Various Locations of Road Shoulders o Continue Working on the Parshall Flume

Three Week Look Ahead (04/19/21-04/23/21) • Pump Station Crew # 1 o Continue Working on Spence’s Trace & RT 137 Pump Station Site’s o Cleanup at Various Locations of Road Shoulders o Continue Working on the Parshall Flume

Please note that this is a projected schedule and will be adjusted accordingly based on the Contractor’s actual progress and the weather. On an as needed basis auxiliary crews will be performing testing, installing inverts, raising castings, paving , and performing general cleanup at various locations throughout the project area.

TOWN OF HARWICH, MASSACHUSETTS SEWERAGE WORKS IMPROVEMENTS PHASE 2
– CONTRACT #2 CONSTRUCTION SCHEDULE –
WEEKLY UPDATE

One Week Look Ahead (04/05-04/09)  Pump Station Crew #1 o Demobilized awaiting building delivery

Two Week Look Ahead (04/12-04/16)  Pump Station Crew #1 o Continue work at Church Street South  Set Building with United Concrete – 4/15

Three Week Look Ahead (04/19-04/23)  Pump Station Crew #1 o Continue work at Church Street south pumping stations o Continue Harden Lane electric and site preparation

Please note that this is a projected schedule and will be adjusted accordingly based on the Contractor’s actual progress and the weather. On an as needed basis auxiliary crews will be performing testing, installing inverts, raising castings, paving , and performing general cleanup at various locations throughout the project area.