MASS DOT CONSTRUCTION NOTICES
Project Location (City/Town): Rte 28, Harwich ___________________________________________________________________________
Estimated Start Date of Work: Mill on Thursday, 11/03/16, pave on Friday, 11/04/16 and traffic markings and markings completed the following week. ___________________________________________________________________________
Project Type: Various Locations Roadway Repairs contract ___________________________________________________________________________
Resident Engineer and Contact Information: Dan Mastrangelo RE, 774-292-2086, Steve Foley, 774-292-2029, or Sean Sigman 774-286-9990 ____________________________________________________________________________
Description of Work: Milling 2 inches and paving roadway followed by pavement markings after at least 48 hours.
____________________________________________________________________________
Contractor and Contact Information: Lawrence Lynch Corp.,
Paving Super. Joe Oliveira 774-836-5033
Construction Super. Matt Cavanaugh is 508-566-2269 _____________________________________________________________________________
Hours of Operations (Day/Night):__7am to 430pm. Day. _____________________________________________________________________________
Description of Traffic Management: The contractor will take and work in one lane at a time while alternating traffic. Advanced warning signs, traffic cones and police details will be utilized.
____________________________________________________________________________
Estimated Duration of Work: Thurs 11/3/16 to 11/4/16, one day to mill, one day to pave and two days to place traffic markings and markers to be done the following week.
____________________________________________________________________________ Additional information: