Project Location (City/Town): Harwich
Estimated Start Date of Work: February 20, 2018
Project Type: Sign Replacement
Resident Engineer and Contact Information: Marc Cardinal 774 286 6383
Description of Work: Retroreflective sign replacement and upgrades on Routes 6A, 28 and 124 from town line to town line or beginning to end.
Contractor and Contact Information: Road Safe Traffic Systems, Inc. : 508-580-6700
Hours of Operation (Day/Night): 7:00 am to 3:30 pm
Description of Traffic Management: Work mainly in the breakdown lane/shoulder.
Estimated Duration of Work: 5 Months
Additional Information:
City/Town Construction Notification Form
MassDOT will be conducting work in your community in the near future. The following project information is being forwarded to you for distribution to affected City/Town Departments.
Project Location (City/Town): Harwich__________________________________
Estimated Start Date of Work: 19MAR18________________________________
Project Type: Rt.124 Park and Ride Resurfacing and Upgrades_______________
Resident Engineer and Contact Information: Malcolm Lavalley (508) 694-5681________
Description of Work: Pavement milling, paving and thermoplastic pavement marking installation with sidewalk and wheel chair ramp reconstruction. Installation of a new bus shelter and bicycle rack. Cleaning of drainage pipes, structures and retention basin. Selective clearing and thinning along existing fence with fence repairs as needed. Other incidental work________________________________
Contractor and Contact Information: Lawrence-Lynch Corp. _____________________
_Superintendent Tony Augusto (508) 566-1503___________________________
Hours of Operations (Day/Night): 7:00am – 3:30pm____________________________
Description of Traffic Management: Traffic Management Plan per Contract, Roadway Flaggers to be used as needed with Police Details to be used for milling and paving operations.__________________________________________________
Estimated Duration of Work: _19MAR18 – 25SEP18___________________________
Additional information: _No work to be performed between Memorial Day and Labor Day________________________________________________________________