Route 6 Roadwork Information *Additional Road Work Attached*

Road Work Sign

 

City and Town Notification for Roadway Work

 

MassDOT will be conducting work in your community in the near future.  The following project information is being forwarded to you for distribution to affect City/Town Departments.

 

Project Location (City/Town):   SANDWICH to EASTHAM Route 6 (Mid-Cape Highway)

 

Estimated Start Date of Work:  Sepember 6, 2017 (after Labor Day)

 

Project Type:  Fabrication and Installation of Ground Mounted Guide and Traffic Signs along a Section of Route 6 (Mid-Cape Highway).

 

Resident Engineer and Contact Information: Richard McKenzie  774-292-2017 cell

 

Description of Work Fabrication and Installation of Ground Mounted Guide and Traffic Signs along a Section of Route 6 (Mid-Cape Highway).

 

 

Contractor and Contact Information:  Liddell Brothers, Inc. (781) 293-2100 office

 

 

Hours of Operation (Day/Night):  Monday thru Friday 7:00 am to 3:30 pm            Work on Rt 6 requiring lane closure Sunday to Thursday 10:00 pm to 5:00 am No lane closure allowed any time on Fridays

 

Description of Traffic Management:  One lane shall remain active at all times

 

Estimated Duration of Work:  Sepember 6,  2017 to  September 29, 2018

 

Additional Information: 

Physical start of work shall be September 2017 (after Labor Day)